Commissioning Readiness Review Worksheet
Original field aid for technicians, engineers and commissioning managers. Use the project's governing requirements and authority structure.
A completed worksheet does not authorise energisation, start-up or transfer of operating control.
1. Identify the review
| Project / facility | Review date / revision | ||
|---|---|---|---|
| System / package / activity | Review lead / participants | ||
| Reference drawings / records | |||
2. Define the intended milestone and boundary
| Milestone and intended operating state | |
|---|---|
| Physical / functional boundary, exclusions and interfaces |
3. Physical completion and evidence
Mark Yes / No / N/A and cite the record. Explain N/A and any incomplete or conditional evidence.
| Review prompt | Yes / No / N/A | Evidence / exception reference |
|---|---|---|
| Defined physical boundary and configuration verified | ||
| Required completion and test evidence accepted | ||
| Instrument / test-equipment identity and validity checked | ||
| Temporary arrangements, isolations and interfaces recorded | ||
| Open punch items and constraints assessed for this milestone | ||
| Required drawings, records and operating information available |
4. Punch items, constraints and blockers
| Item / constraint and reference | Consequence for this milestone | Required control / action owner |
|---|---|---|
Use the project punch convention. A high progress percentage does not override a blocker.
5. Procedures, resources and interfaces
Project / system / review reference: __________________________________________
| Review prompt | Status | Reference / gap / owner |
|---|---|---|
| Procedure / method and correct revision | ||
| Competent people, roles and specialist support | ||
| Tools, instruments, consumables and facilities | ||
| Construction, vendor, client, Class and operations interfaces |
6. Authorisation and operating-control checks
| Required check | Status | Authority / evidence / condition |
|---|---|---|
| Required permit / isolation / control-of-work checks | ||
| Authorised operating state and operating-control holder | ||
| Protective functions, emergency response and stop controls | ||
| Required witnesses, hold points and release authority |
7. Actions and follow-up
| Action / linked constraint | Owner | Due date | Closure evidence / reviewer |
|---|---|---|---|
8. Decision record and review triggers
Review recommendation: ☐ Hold ☐ Conditional recommendation ☐ Recommend consideration for authorised release
| Decision, conditions and residual constraints | |
|---|---|
| Responsible decision-maker / date / reference | |
| Next review / triggers to reopen this decision |
Review again after relevant configuration, scope, procedure or operating-state changes; new defects or blockers; expired conditions; or a failed test. Apply the project's own review triggers.
This is a review record, not an operating permit or automatic release. Record any subsequent authorisation separately through the responsible project process.
Original worksheet · Elvis Rigby · emrigby.com · Not a client or employer standard.