Commissioning Readiness Review Worksheet

Original field aid for technicians, engineers and commissioning managers. Use the project's governing requirements and authority structure.

A completed worksheet does not authorise energisation, start-up or transfer of operating control.

1. Identify the review

Project, system and review identity
Project / facilityReview date / revision
System / package / activityReview lead / participants
Reference drawings / records

2. Define the intended milestone and boundary

Milestone and intended operating state
Physical / functional boundary, exclusions and interfaces

3. Physical completion and evidence

Mark Yes / No / N/A and cite the record. Explain N/A and any incomplete or conditional evidence.

Review promptYes / No / N/AEvidence / exception reference
Defined physical boundary and configuration verified
Required completion and test evidence accepted
Instrument / test-equipment identity and validity checked
Temporary arrangements, isolations and interfaces recorded
Open punch items and constraints assessed for this milestone
Required drawings, records and operating information available

4. Punch items, constraints and blockers

Item / constraint and referenceConsequence for this milestoneRequired control / action owner

Use the project punch convention. A high progress percentage does not override a blocker.

5. Procedures, resources and interfaces

Project / system / review reference: __________________________________________

Review promptStatusReference / gap / owner
Procedure / method and correct revision
Competent people, roles and specialist support
Tools, instruments, consumables and facilities
Construction, vendor, client, Class and operations interfaces

6. Authorisation and operating-control checks

Required checkStatusAuthority / evidence / condition
Required permit / isolation / control-of-work checks
Authorised operating state and operating-control holder
Protective functions, emergency response and stop controls
Required witnesses, hold points and release authority

7. Actions and follow-up

Action / linked constraintOwnerDue dateClosure evidence / reviewer

8. Decision record and review triggers

Review recommendation: ☐ Hold   ☐ Conditional recommendation   ☐ Recommend consideration for authorised release

Decision, conditions and residual constraints
Responsible decision-maker / date / reference
Next review / triggers to reopen this decision

Review again after relevant configuration, scope, procedure or operating-state changes; new defects or blockers; expired conditions; or a failed test. Apply the project's own review triggers.

This is a review record, not an operating permit or automatic release. Record any subsequent authorisation separately through the responsible project process.