| Systemisation and boundary definition | Design and scope sufficiently developed | Break the asset into controllable systems and define physical, functional and responsibility boundaries | System list, marked drawings, boundary and interface records | Agreed basis for completion and commissioning control |
|---|
| Construction completion | Installation work released for inspection | Finish and inspect the defined construction scope | Inspection and test records, redlines, defect and punch records | Defined scope available for mechanical-completion review |
|---|
| Mechanical completion | Required construction and inspection records available | Confirm the agreed boundary is installed and inspected, subject to accepted exceptions | Inspection and test records (ITRs), walkdown record, punch list and certificate | Accepted release for specified pre-commissioning work |
|---|
| Pre-commissioning | Mechanical-completion prerequisites and controls accepted | Prepare and prove equipment or systems before functional operation, using the approved scope | Cleaning, calibration, continuity, pressure, loop or other project-defined records | Defined system condition available for commissioning |
|---|
| Commissioning | Approved procedure, utilities, interfaces and readiness evidence available | Demonstrate integrated function within a controlled test envelope | Functional tests, settings, exceptions, trends and witnessed results | Accepted readiness for the next defined operating state |
|---|
| Start-up or initial operation | Required commissioning and operational-readiness gates accepted | Introduce the system to its intended operating state under authorised control | Start-up record, operating parameters, deviations and stabilisation evidence | Stable condition for continued operation or performance testing |
|---|
| Performance testing | Stable configuration and agreed test conditions established | Compare measured performance with contract or project acceptance criteria | Test method, calibrated data, conditions, calculations and accepted result | Performance result accepted, rejected or conditionally closed |
|---|
| Acceptance | Required technical evidence and exceptions presented | Make the defined technical or contractual acceptance decision | Certificate, approval, reservations and action ownership | Accepted status and responsibilities recorded |
|---|
| Turnover and handover | Transfer boundary, evidence and receiving authority agreed | Transfer the system, its known condition, records and remaining obligations | Dossier, turnover package, operating information and handover record | Receiving organisation assumes the stated responsibility |
|---|